Becker's has reported on three hospitals or health systems experiencing infrastructure issues with its construction since Nov. 15:

  1. Paramus, N.J.-based Valley Hospital experienced a settling issue during the construction of a parking garage. The issue did not affect the main hospital campus and will not delay the end of 2023 opening.

  2. A crack was found and repaired on Columbus-based Ohio State University Wexner Medical Center's $1.9 billion hospital tower. The crack did not delay the opening. 

  3. De Queen, Ark.-based Sevier County Medical Center was delayed in its opening because of the theft of construction materials.