New cost estimate for Colorado VA medical center: $1.73B

The U.S. Department of Veterans Affairs estimates that a new VA Medical Center in Aurora, Colo., will cost $1.73 billion, an amount more than five times higher than the initial projected cost of $328 million, according to a report from The Denver Post.

The new estimate represents the most recent setback for the project, which was temporarily suspended in December 2014 due to a dispute with prime contractor Keiwit-Turner.

The $1.73 billion-estimate, VA officials said, is based on research that was provided by the U.S. Army Corps of Engineers, which agreed to oversee the project following the VA's latest dispute with Keiwit-Turner, according to the report.

"The estimate includes the cost of construction, contingencies, and Army Corps of Engineers costs, as well as VA's cost to close out the original contract and continue construction until the Army Corps of Engineers assumes construction management duties this summer," VA Deputy Secretary Sloan Gibson wrote in a letter to Congress, according to the report.

In his letter to Congress, Mr. Gibson estimated that the VA was working to reprogram about $100 million toward the project, but that there was an "additional funding need of $830 million."

 

More articles on healthcare finance:

Children's Hospital to expand onto former Marine Hospital campus

Oregon hospitals roll out new charity care policies

UMass Memorial severs ties with UniCare after years of negotiations

Copyright © 2024 Becker's Healthcare. All Rights Reserved. Privacy Policy. Cookie Policy. Linking and Reprinting Policy.

 

Featured Whitepapers

Featured Webinars

>