Sarasota (Fla.) Memorial Health Care System launched Epic across its hospitals, outpatient centers and physician offices in early October, closing out a roughly $160 million project. Software wasn’t expected to be the big line item.
CIO Pam Ramhofer explained to Becker’s in 2025 that Sarasota Memorial’s software costs would stay in line with what it was already paying, with the bulk of the investment going toward the implementation.
That split is common. The price tags health systems attach to Epic projects largely measure what they spend on themselves: employees pulled onto project teams, new hires, consultants, trainers, travel, devices and infrastructure. The contract with the EHR vendor is often a minority share.
Houston Methodist’s numbers show how lopsided the split can be. People costs consumed 72% of the health system’s $293 million, three-year Epic project, then-CIO Robert Eardley wrote in a 2017 column for Becker’s. Software made up 10% of the budget and hardware 9%. The project team numbered 226, supplemented by 60 trainers at peak and 350 activation support staff for go-lives.
After reviewing the spending, the health system’s senior vice president of finance put it simply, Mr. Eardley wrote:
“I get it now, this is a people project.”
Epic has made the same case. In 2016, Eric Helsher, then Epic’s vice president of client success, argued that pinning a full implementation budget on the vendor is misleading because any EHR install also requires servers, storage, laptops and mobile devices.
“That would be like if you go buy a fully loaded laptop and attribute that full cost to Microsoft Word. You needed the computer to get Word,” Mr. Helsher said.
The labor shows up in headcount. At Rockledge, Fla.-based Health First, roughly 85 of the system’s 350 or so IT employees worked full time on its Epic implementation, plus another 65 from project management, operations and clinical roles, CIO Michael Carr detailed in 2024. About 1,000 employees took part in the project, which he estimated would take at least “a couple hundred thousand hours” of work.
Sarasota Memorial similarly had about 1,000 staffers on its project, including 30 new full-time employees hired specifically for Epic, along with project management consultants.
Ms. Ramhofer said keeping the work in-house was deliberate.
“We try to use our own staff as much as possible, because there’s a lot of knowledge that’s gained when you build a system, and I don’t want that walking out the door,” she said.
Some of that staff time is spent in Wisconsin. Health system employees travel to Epic’s Verona campus to get certified for roles such as Epic analyst, in stays of a handful of days that add up to several weeks, Becker’s reported in 2025. About 100 employees of Mullica Hill, N.J.-based Inspira Health made the trip ahead of the four-hospital system’s July go-live.
The trips don’t stop at launch. Health systems send staff to Epic’s Users Group Meeting and Expert Group Meetings, in part to earn rebates on their EHR costs, and the size of the delegation is itself a budget decision.
“We only sent about 15 people this year because we’re stretched a little financially now,” David Kaelber, MD, PhD, chief health informatics officer of Cleveland-based MetroHealth, said in 2025.
Outside help lands on the income statement too. Brentwood, Tenn.-based Ardent Health disclosed $3.1 million in professional fees tied to its Epic rollout in 2024, up from $1.8 million in 2023, according to a February 2025 financial report. Those figures didn’t include ongoing maintenance costs. Minneapolis-based Children’s Minnesota, which budgeted about $175 million for its Epic transition, is working with implementation partners while keeping its internal teams responsible for execution.
Because so much of the money is internal, the headline figures are hard to compare. There is no standard way to build an implementation budget, Randy Carpenter, a senior vice president at Stoltenberg Consulting, explained in 2016: Some health systems count the salaries of employees already on the payroll and the new devices they buy, and some don’t.
The University of Alabama System’s board approved a roughly $380 million budget for UAB Health System’s Epic move in 2024 that covers implementation and some labor and operations for seven years. Health First’s $160 million estimate, by contrast, excluded the cost of running the EHR once it went live.
Some of the spending is offset by what Epic replaces. Health First planned to turn off 122 applications, and Sarasota Memorial expected to retire nearly a quarter of its roughly 380 applications.
“We pay a lot more for that current portfolio of systems than we’re going to pay for Epic once we’re live,” Mr. Carr said.
Epic is the largest IT project in Ms. Ramhofer’s 40 years at Sarasota Memorial, and one of the health system’s biggest capital investments overall.
“In terms of touching people, it’s No. 1, because about 80-90% of our staff is going to be touched by it somehow, as well as our entire community that uses our services,” she said.