The hospital’s board of regents will meet next week to approve the higher cost, four years after initially discovering problems with the windows on floors four and five. After further investigation, hospital officials now believe windows on floors three through 11 need replacing.
With the $45 million window project and another $16 million that the hospital was ordered to pay a contractor, the hospital’s total construction cost could reach $450 million, a 66 percent increase from the initial cost estimate. The hospital opened in 2017.
At the Becker's 11th Annual IT + Revenue Cycle Conference: The Future of AI & Digital Health, taking place September 14–17 in Chicago, healthcare executives and digital leaders from across the country will come together to explore how AI, interoperability, cybersecurity, and revenue cycle innovation are transforming care delivery, strengthening financial performance, and driving the next era of digital health. Apply for complimentary registration now.