Construction on the 440,770-square-foot project began in 2021, according to the report. The project will create 200,000 square feet of lab space with a new facade, conference rooms and other spaces. The Children’s Center moved in 2012 and the building has mostly sat vacant.
The budget for the project has increased from $400 million when it was presented to city officials in November 2019 to $515.9 million, according to the report. The project was originally planned to be completed in spring 2023. Both the increased cost and timeline have been attributed to supply chain issues during the COVID-19 pandemic.
Becker’s 3rd Annual Fall Chief Pharmacy Officer Summit is the top tier event that the people leading the future of pharmacy convene. This 3-day event is built specifically for Chief Pharmacy Officers and senior pharmacy leaders. The sessions examine the workforce, financial and clinical priorities shaping pharmacy today. Becker’s is where candid discussions flourish and new ideas thrive. Becker's 3rd Annual Fall Chief Pharmacy Officer Summit