Inside UPMC Presbyterian’s $1.3B bet for ‘the next 100 years’

Advertisement

About a decade ago, leaders at Pittsburgh-based UPMC had to decide what to do about the inpatient tower at UPMC Presbyterian, which is about 100 years old. Renovating it would have taken about 17 years while the building stayed open to patients, cost almost as much as new construction and eliminated 150 beds.

It opted instead for a new building, which is about two months from opening. The 17-story, $1.3 billion UPMC Presbyterian Daniel G and Carole L Kamin Tower is set to receive patients Jan. 24, when staff plan to move between 550 and 600 patients into the UPMC Presbyterian Kamin Tower in a single day.

“Our last facility took us through the last 100 years, and now this one will take us through the next 100 years,” Sandy Rader, DNP, president of UPMC Presbyterian Shadyside, said during an episode of the “Becker’s Healthcare Podcast.” “Most of us here feel like this is a once-in-a-career opportunity, and we’re very, very proud.”

Dr. Rader, a nurse by background, has been with UPMC for about 26 years. She has served as president for about four years, after previously serving as COO and chief nursing officer.

The project grew out of UPMC’s analysis of whether to renovate its existing inpatient tower or build a new one. Once leaders saw what renovation would cost in time, money and beds, building new became an easy decision, Dr. Rader said. UPMC broke ground in June 2022, and the system has called the tower its largest construction project to date. The 900,000-square-foot building will have 636 private rooms and 450 adjacent parking spaces, according to UPMC. In July 2025, the system received a $65 million gift from Daniel G. and Carole L. Kamin and the Kamin Family Foundation, and the tower was named in their honor.

Dr. Rader said the project gave UPMC a chance to consider where healthcare is headed and to build in safety and respite features for staff. The goal, she said, was to advance what the system calls the UPMC experience: being the best place for patients to receive care, for people to work and for physicians to practice.

She credited engagement from a local steering committee at UPMC Presbyterian and a systemwide executive steering committee with keeping the project on time and on budget. The team spent four years planning with front-line staff before construction started, set timelines for decisions and held to them.

“We were building this in the middle of COVID, so the budget would be tight, and then it would be on track again,” Dr. Rader said. “We really paid close attention to that as we came through those difficult financial years to erect this tower in the right way.”

Hours spent with patients and community members shaped features not typically found in a hospital, she said. The first four floors, known collectively as the Grove, are built for the community. The first floor includes a full-service restaurant, a Starbucks and a lobby. The second floor houses a spirituality center with a traditional chapel, private spaces for families, an ablution room, a kosher kitchenette and a gym for families of patients with long stays. The third floor serves as a community center with conference space and a demonstration kitchen for classes, such as those for community members with diabetes.

“We’ll have a demonstration kitchen there because the community said to us, ‘We don’t want you to just tell us what to do. We want you to show us,'” Dr. Rader said.

The fourth floor includes a cafeteria called the Galley at the Grove and a sky lobby with a family business center, where relatives staying with loved ones can reserve a room for video calls and other work. A market positioned along staff members’ route out of the building will sell groceries such as bread and eggs, along with prepared meals.

In patient rooms, large screens on the foot walls will serve as entertainment, communication and education centers. Patients can video chat with family members and pull up chart information, scans and lab results, and cameras in every room support remote monitoring.

Dr. Rader acknowledged that much of healthcare is moving to outpatient settings and the home. But the hospital serves some of the most complex patients, she said, as a level 1 trauma center that performs more than 400 transplants a year and provides advanced cardiac, vascular and neurosurgical care. The tower includes a hybrid room for cardiac care.

“So while much of healthcare is shifting to outpatient sites, we know there are still many, many very complex patients who need a setting like this,” she said.

The tower will also use hundreds of AI-powered cameras that can alert security teams when they detect people congregating in one area, aggressive behavior or a weapon, Dr. Rader said.

Planning for move day has been underway for 18 months. Nursing units are assigned to five tracks, each with move teams. Clinical leaders will arrive about 3 a.m. to review the sequence of patient moves, and nursing staff will arrive at 7 a.m. to complete assessments, serve breakfast and give morning medications. At 9 a.m., moves will begin across all five tracks at once, with a medical-surgical patient moving every three minutes and an ICU patient every five minutes. Move teams for critical care patients will include a critical care physician. Dr. Rader expects the work to finish around 5 or 6 p.m.

“If I’m the nurse caring for that patient, I continue to care for that patient, and the move team descends on that room,” she said.

For hospitals considering a major construction project, Dr. Rader advised preparing for a long process with many decisions, investing heavily in planning and including every stakeholder. UPMC built a mock patient room offsite and sent staff nurses there to weigh in on where everything should go.

“We wanted every single room to look exactly the same, and we knew that if we made a mistake, we were making it 636 times, because there are 636 beds in this tower,” Dr. Rader said. “So allow yourself the time, the patience and the commitment to really get into every single detail and involve all of your stakeholders.”